Economic Development Council - MCCAdams Grant Task Force

Streetscape & Virtual Cultural Center

NOTES Subcommittee meeting 9/11/06

Meeting Room A, Town Hall

 

Present:   Michelle Jarusiewicz/Acting Asst Town Manager, Hunter O’Hanian/FAWC/EDC, Candy Collins-Boden/Chamber, Alix Ritchie/Banner/EDC, Don Knuuttila/PBG

 

ICON & Charrette #1: General discussion about the proposed schedule and approach submitted by ICON which includes scheduling Charrette #1 during the 1st week of October. All agreed that, before we could schedule the Charrette, we – the subcommittee and the task force – need to meet with ICON to share ideas, review their preliminary thoughts, and discuss process. This is too important and it needs to be done right.

 

Step 1: schedule conference call with subcommittee and ICON

Step 2: schedule meetings, suggested dates:

Thursday, 9/28 for subcommittee

Step 3: and Friday, 9/29 with full MCC Adams Task Force

 

This will probably bump the Charrette until the end of October.

 

Timeline: Adams grant goes through December 31, 2006, but County EDC grant [primary grantor of Streetscape component] goes until May 2007 which allows more time for the project with ICON. Keep in mind Provincetown’s Annual Town Meeting [April  2007] and the need to repair the streets, thus we need to have direction by February 2007 prior to the closing of the warrant.

 

Streetscape Discussion:

General discussion notes:

Streetscape project should connect the dots – the primary dots being the cultural assets.

Multi-layering: not changing Provincetown, just adding to the chaos.

 

Think: